Commissioning is a sequence with defined entry and exit conditions at each step, not a single event called "testing".
Overview
- Step order: mechanical integration, power-up checks, interface communication, functional test, then flight test preparation.
- Each step has an exit condition; the next step does not start while it is unmet.
- Every measurement is recorded against the unit's serial number on the day it was taken.
- Any rework sends the unit back to the last step whose exit condition is no longer satisfied.
Related pages
- Technical StrengthView
- Company overviewView
- Development Testing and DeliveryView
- Procurement and Selection GuidesView
More in this area
- Production and Delivery OrganizationRead
- Manufacturing Stages and Responsibility SplitRead
- Incoming Component InspectionRead
- Assembly and Configuration ManagementRead
- Integration and Commissioning ProcessThis page
- Ground Functional ChecksRead
- Flight Test SchedulingRead
- Serial Number and Delivery TraceabilityRead
- Packing and Shipment InspectionRead
- Capacity Lead Time and Volume Delivery BasisRead